January 27, 2014
Construction on Servicon System's Hangar Office is rapidly progressing! Outside, the 56 kilowatt solar photovoltaic system, consisting of 227 roof-mounted panels and a solar carport structure, is on and humming, generating free, clean electricity. This system also greatly contributes to securing our anticipated LEED-Platinum rating. Inside, painting is progressing, restrooms are tiled, mechanical ductwork is installed, and dropped ceilings are ongoing. Left to be installed: millwork, corrugated metal cladding, carpet, glazing, and floor coatings.